Excel I am trying to create the following for my company and am stumped: Start Date * Rate of Starts per week(WORKDAY) = Finish Date I would like to change the rate of starts to give the finish date. Please help

3 Answers

martin hogg

Level 2:

An expert who has achieved level 2 by getting 100 points

MVP:

An expert that got 5 achievements.

Governor:

An expert whose answer got voted for 20 times.

Scholar:

An expert who has written 20 answers of more than 400 characters.

  • Expert 157 Answers
  • Posted on Jan 08, 2008
martin hogg
Expert
Level 2:

An expert who has achieved level 2 by getting 100 points

MVP:

An expert that got 5 achievements.

Governor:

An expert whose answer got voted for 20 times.

Scholar:

An expert who has written 20 answers of more than 400 characters.

Joined: Dec 14, 2007
Answers
157
Questions
0
Helped
76413
Points
263

Like previous poster, I'm guessing that you want something like this......Whate we need to know is : what formats do you need for Dates and Rate ?

Start Date Rate per Workday Finish Date

A

Anonymous

  1. GFK'
  2. GSDFG,'SDF
  3. GDS',G

Ad

DavidPerich

Level 2:

An expert who has achieved level 2 by getting 100 points

All-Star:

An expert that got 10 achievements.

MVP:

An expert that got 5 achievements.

Sergeant:

An expert that has over 500 points.

  • Expert 272 Answers
  • Posted on Dec 29, 2007
DavidPerich
Expert
Level 2:

An expert who has achieved level 2 by getting 100 points

All-Star:

An expert that got 10 achievements.

MVP:

An expert that got 5 achievements.

Sergeant:

An expert that has over 500 points.

Joined: Dec 27, 2007
Answers
272
Questions
3
Helped
93084
Points
720

Your issue is not stated very clearly so I'll make some guesses about your problem.
I'm guessing you mean "rate" (Starts-per-Week) is the number of starts you have that week.
I'll guess that those starts are not new start dates but something else-maybe job starts.
Each start implies a job duration period. Do you want to know the finish date of each job or are you only interested in when the last job will be completed? Don't think I can give you meaningful Excel formulas at this time.
Maybe Excel is the best tool for this job but I suspect someting like Microsoft Project would be more appropriate (but expensive). You should Google "project tracking", "project orgainization" and "Gant chart" and read what you find to get a good feel for your problem and how to solve it.

Add Your Answer

×

Uploading: 0%

my-video-file.mp4

Complete. Click "Add" to insert your video. Add

×

Loading...
Loading...

Related Questions:

tip

How to use System Restore

You can access System Restore through <b>Help and Support</b> or through your <b>All Programs folder</b>. <br /><b>Through Help and Support:</b><br />Click <b>Start</b>, and then click <b>Help and Support</b>.<br />Under <b>Pick a Task</b>, click <b>Undo changes to your computer with System Restore.</b><br />Follow the instructions on the wizard.<br /><b>Through the All Programs menu:</b><br />Click Start. Select <b>All Programs</b>. Select <b>Accessories</b>. Select <b>System Tools</b>. <br />Click <b>System Restore</b>. <br />Follow the instructions on the wizard<br /><b>How to Create a Restore Point:</b><br />Open System Restore. <br />Select <b>Create a restore point</b>, and then click <b>Next</b>.<br />In the <b>Restore point description</b> box, type a name for your restore point. System Restore automatically adds the date and time that this Restore Point is created.<br />To finish creating this restore point, click <b>Create</b>.<br />
on Jul 11, 2011 • Computers & Internet
0helpful
1answer

Workday function in excel formulas

The WorkDay Function returns a number that's the serial date that is the indicated number of working days from a given date (the starting date). Working days EXCLUDE weekends and any dates identified as holidays. Use WORKDAY to exclude weekends or holidays when you calculate invoice due dates, expected delivery times, or the number of days of work performed.
The Syntax is:
=WORKDAY(start_date,days,holidays)
where:
- start_date is in Date format (and can be a calculated value);
- days is a number of elapsed days after start_date (can be calculated, can be negative to indicate a date BEFORE start_date);
- holidays is an array of holidays you can specify if desired.
12helpful
1answer

I can't set the time on the Timex 1440

To set the time on your Timex 1440 Watch, please follow these directions:

1. Press and hold MODE (Upper left button)
(HOURS will flash and you'll be in Alarm Mode).

2. Press MODE again to enter TIME mode.
(SECONDS digits will flash.)

3. Press ADJUST (bottom right button) to set SECONDS to zero.

4. Press START/STOP (upper right button) to select MINUTES

5. Press ADJUST to change

6. Repeat to set Hours, Date, Month, and Day of the week.
(Go through 12 hours to set AM or PM)

7. Press MODE when finished

8. To display DATE from TIME display, press START/STOP

9. With DATE displayed, press and hold START/STOP, then press ADJUST to change display between DATE-MONTH

10. With TIME displayed, press and hold ADJUST, then press MODE to switch between 12 and 24 hour format.
I hope you are now able to set the time on your watch! If you appreciate these instructions, please remember to rate this post.

--Sandy

0helpful
1answer

I have 10 not 9 i i install the program and now my computer wont do anything the screen is black i tired the f8 but that didnt work either

As soon as your computer boots press and hold F8 Key to start it in Safe Mode or in Last Known Good Configuration.
I recommend you to start in a Safe Mode. Assuming you are running windows 7, click on "Start" Menu and type "System Restore".
Follow the screen and choose a date before you started installing your new software. After finishing wizard it will reboot and should work normally. However you need to reinstall the software because it might not be there after restore.

WARNING:- You might loose all the new data or files you created on or after that date, therefore before starting "System Restore" get the backup of all date you have created on and after the date.
0helpful
1answer

REQUIRE EXCEL TIMESHEET Thursday to Wednesday. With DAY, date, start and end times with 1, 30 MIN meal break, total hours for the day (not to exceed 7), any time over 7 THEN GOES TO TIME IN LEIU COLLU

Here are already prepared template time sheets of which your description fits several.

http://office.microsoft.com/en-gb/templates/CT101172771033.aspx?av=ZXL000
0helpful
1answer

FORMULA NEEDED FAST

Yes you can create the formula outside the cell or you can create it one time and copy it down to the other cells. That way it will populate once it is used.

The formula should be Base Rate * .05 to get the result then add the result back to the base rate.
0helpful
3answers

Need excel solution

Hello ycool11, If your asking what i think you are the formula would be
=(a2-a1)*24
That assumes a2 is that last date entered and a1 is the initial starting date. if you would like a more intense formula let me know and i'm sure i can help.
0helpful
1answer

CAN'T CALCULATE DATES TO GIVE DEADLINE

cell 1 (date format) = start date
cell 2 (number format) = number of days = cell 3 - cell 1
cell 3 (date format) = deadline = cell 1 + cell 2
Not finding what you are looking for?

123 views

Ask a Question

Usually answered in minutes!

Top Microsoft Computers & Internet Experts

Grand Canyon Tech
Grand Canyon Tech

Level 3 Expert

3867 Answers

k24674

Level 3 Expert

8093 Answers

Brad Brown

Level 3 Expert

19187 Answers

Are you a Microsoft Computer and Internet Expert? Answer questions, earn points and help others

Answer questions

Manuals & User Guides

Loading...